Reconstruction of Banići gas center
-
Name of the project
Reconstruction of Banići gas center
-
Project Details
Investor: Dubrovnik plin d.o.o.
Gross building area: 6000 m2 -
Construction duration
Commencement date: March 24, 2017
Completion date: June 23, 2017 -
Location
Banići
Project details
Construction of the regional gas center in Banići performed at the highest standards includes the construction of the new gas station together with the road. Within the gas station the LPG filling station, compressor stations, offices, gas tanks and associated facilities were built. The bottling and distribution of LPG in the bottles and the supply of gas tanks for the whole region is carried out right in Banići gas center. The entire hydrant network as well as the precipitation drainage system has been performed.